Most significant this week is the progress in the galley and the engine room. Enjoy the photos.
![]() |
1. Starboard profile. Finish work on the fashion stripe Stainless steel stanchions installed on the forward deck |
![]() |
2. Aft deck. Fiberglass support struts with whole for running drains. Hole will be filled Tape on the salon bulkhead suggests preparation for sink, water and storage cabinetry |
![]() |
3. Fiberglass work continues on the hardtop. Seams still look rough Installation perhaps in the next two weeks? |
![]() |
4. VIP SR. No change |
![]() |
5. Guest SR. No change |
![]() |
6. Master SR. Cabinetry for washer and dryer locker epoxied |
![]() |
7. Master SR looking aft. No change. Surfaces are protected |
![]() |
9. Pilot house AC vent to the right of the worker's head Veneer applied to the side of the settee |
![]() |
10. Galley Overhead cabinets and sink installed Cut-out for the GE Monogram cook top Cabinetry for the microwave |
![]() |
11. Salon looking forward Structure in place for recessed ceiling with stainless steel hand holds |
![]() |
12. Salon looking aft. No change |
![]() |
13. Engine room looking forward Stainless steel protection rails installed Light switch in port bulkhead |
![]() |
14. Engine room looking aft. Workers protecting the new rails |
![]() |
15. Lazarette looking to starboard. Wiring on the bulkhead Cabinetry under work bench |
![]() |
16. Lazarette looking to port. No change |
![]() |
17. Lazarette looking aft Motor for Glendenning shore power 50 amp electrical cord (left side just visible) Shelves installed on starboard side storage locker
|