Thursday, September 19, 2013

Construction: Week 39 - Sink, Rails & Overhead Cabinets

The photos came Thursday due to Friday being a Chinese holiday.  As always there is progress in almost every area as the project moves into the final weeks of completion, which is estimated to be the end of November.

Most significant this week is the progress in the galley and the engine room.  Enjoy the photos.


1. Starboard profile. 
Finish work on the fashion stripe
Stainless steel stanchions installed on the forward deck
2. Aft deck. 
Fiberglass support struts with whole for running drains.  Hole will be filled
Tape on the salon bulkhead suggests preparation for sink, water and storage cabinetry

3. Fiberglass work continues on the hardtop.  Seams still look rough
Installation perhaps in the next two weeks?
4. VIP SR.  No change

5. Guest SR.  No change

6. Master SR. Cabinetry for washer and dryer locker epoxied

7. Master SR looking aft. No change.  Surfaces are protected

8. Pilot house
Teak veneer being installed
Windshield wiper motors installed
Trap doors for wiper motor access (under shelf above windows)
Plumbing for windshield washers running up window mullions
Shelf and struts for overhead cabinetry housing electronic equipment

9. Pilot house
AC vent to the right of the worker's head
Veneer applied to the side of the settee

10. Galley
Overhead cabinets and sink installed
Cut-out for the GE Monogram cook top
Cabinetry for the microwave

11. Salon looking forward
Structure in place for recessed ceiling with stainless steel hand holds

12. Salon looking aft.  No change

13. Engine room looking forward
Stainless steel protection rails installed
Light switch in port bulkhead

14. Engine room looking aft. Workers protecting the new rails

15. Lazarette looking to starboard.  Wiring on the bulkhead
Cabinetry under work bench

16. Lazarette looking to port.  No change

17. Lazarette looking aft
Motor for Glendenning shore power 50 amp electrical cord (left side just visible)
Shelves installed on starboard side storage locker
 


Friday, September 13, 2013

Construction: Week 38 - Fashion Stripe & Electrical Panels

Things continue to move along with progress as usual evident in every area.

1. Port side view of the black "fashion stripe"

2. Starboard view of the fashion stripe

3. Flybridge and boat deck - No change

4. Hardtop sections mated and awaiting fiberglass finishing on seams.  Installation may occur this week.

5. VIP - No change

6. Guest SR drawers veneered

7. Master SR with berth storage areas sealed with epoxy paint

8. Master SR looking aft. Aft storage lockers veneered and drawer area covered with  epoxy paint

9. Pilot House with dash board framed out and DC Main Panel installed in cabinet

10.  Pilot House with platform for table and worker installing wiring for the AC Main Panel

11. Galley looking to port with the above counter cabinets awaiting installation. 
Epoxy paint in cabinets

12. Salon looking forward.  Windows framed, bulkhead veneered and above counter galley cabinets sitting on galley counter

13. Salon looking aft.

14. Engine Room looking forward - No change

15. Engine Room looking aft.  Continue work on wiring in the upper right corner.

16. Lazerette looking forward. Heavy duty wiring for the Inverter on port bulkhead.  Rotary switch under inverter.
Another rotary switch for battery control on starboard bulkhead.

17. Lazerette looking to port.  Port portlight installed.  Sight gauge mount next to extension cord

18. Lazeretter looking to starboard. Sight gauge top and bottom mounts visible

Friday, September 6, 2013

Construction: Week 37 - Flybridge and Boat Deck

I checked my email around 12:30 PM and discovered that Jeff Druek had sent my Friday photos. However, I though it was Thursday and that the photos were early.  Somehow I had lost a day.  Oh well.

Meanwhile this week's photos are very exciting.  The big event that I had been expecting for weeks finally happened.  The yard mounted the flybridge and boat deck assembly to the house. 

Other progress is found in the salon where the yard corrected last week's incorrectly installing teak bullnose with the correct wenge.  The other significant progress is in the pilot house where we can see the beginnings of the control panel.

Let's start with the flybridge and boat deck assembly.  Last week we saw it finally turned right side up on the yard floor.  This week the assembly was secured to the hull with 3M Marine Glue and stainless steel bolts spaced approximately 6 inches apart.  The attachment area is probably in the process of being glassed over and gel coated.

The flybridge / boat deck assembly facilitates the fully covered aft deck, a visor over the flybridge and acts as covers over the port and starboard walkways.

1. Hull with flybridge / boat deck assembly attached to the house


2. Flybridge as viewed from the boat deck.
Note the control station (center) and hatch leading to pilothouse stairwell (right). 
Storage areas are visible to starboard on the boat deck

3. Great view of the fully covered aft deck and port walkway visible.
Stainless steel support posts will ultimately be installed
Boxes on the port walkway under salon windows are air intakes for the engines

4. VIP.  No change

5. Guest stateroom.  No change

6. Master SR looking forward.  No changes

7. Master SR look to port. End tables tops are protected

8. Master SR looking aft. Cables in port hanging locker are bundled

9. Pilothouse with instrumentation cutouts and platform for Stidd helm chair

10. Pilothouse looking to port with satin finish on settee frame.
Storage area behind settee cushion
An appliance just to the left of the worker may be the microwave oven

11. Galley looking to port.  Cabinetry for microwave is new

12. Salon looking forward.  Teak bullnose replaced with wenge

13. Salon looking aft.  Wenge tops and bullnose.  Window boxes being constructed

14. Engine room looking forward.  Note the hoses and cables by the hatch.
Louvers for fire suppress system.
Hydraulic system valves and couplings in box forward of the hoses.

15. Engine room looking aft.  Parallel switch panel and gauges for generator installed on port bulkhead
Overhead lights installed

16. Lazarette looking to starboard.  Workbench and port hole with dead light installed.
Storage cabinet doors visible to your right
Explanatory Note: The port hole consists of a stainless steel frame, a glass cover, which is can be opened to let air in, and the dead light cover  The dead light cover consist of a frame with a rubber gasketed around a stainless steel cover with dogs (fasteners).  The dead light allows the port hole to be completely secured in the event of rough seas.

17. Lazarette looking to port.  Again storage cabinet doors visible to your left. 
Freezer will be installed aft of the auxiliary fuel tank


18. Lazarette looking aft.  New storage cabinet door fame to starboard

Note: Many of the photos include workers suggesting that 63-063 (her official number) is on the fast track for completion.

There are now 5 weeks until my visit to the shipyard (10/10 to 10/18 including travel) and 12 weeks to expected completion at the end of November.

Written by Les.