News:
- Shipping Date: December 19, 2013
- Arrival in Florida: Around January 22, 2014
1. At the dock in Taiwan |
2. Transom, swim platform and aft deck |
3. Flybridge |
4. Flybridge controls Stidd helm chair base |
5. Boat deck Soft wire rail installed aft (Note: Facilitates removal of the dingy) |
6. VIP Stateroom - Finished Drawers under bunk |
7. Guest stateroom - Finished |
8. Master stateroom Wenge headboard surround Note: Coin dot engine room flooring on master berth |
9. Master looking aft Cabinet door installed (just to the right of the engine room access door) |
10. Pilot house Worker installing stidd helm chair base |
11. Pilot house looking to port Settee table installed 110 volt outlets |
12. Galley looking aft Teak panel installed on trash compactor Lift switches to the right of the trash compactor |
13. Salon looking forward Floor protected for shipping |
14. Salon looking aft Stainless steel table leg visible Awaiting installation of the table |
15. Engine room looking forward Awaiting coin dot flooring |
16. Engine room looking aft |
17. Lazarette looking forward Door frame installed Note: Awaiting installation of the water tight door |
18. Lazarette looking aft Ladder from the swim platform to the lazarette |
Written by Les.