Friday, November 22, 2013

Construction: Week 48 - More Finishing Touches & Complete Photos

This morning at 8:00AM, just for fun, I emailed Mike at Outer Reef complaining that the photos were late.  They arrived one minute later at 8:01AM (sent by Jeff Druek, President of Outer Reef). These darn photos are like crack cocaine (in principle as I never indulge).  It only took one minute to get my fix.  Sadly we will be soon reaching a blackout period when the boat ships.  Maybe I'll take up the real thing on Friday mornings.

Other news.  The sea trial actually took place last Thursday (November 14).  I received the report on Tuesday of this week.  More on this in a separate article entitled "Construction: Week 48 - Sea Trial in Taiwan."

This week's photos are a special treat with views of the entire boat.  Special thanks to Howard Chou at Tania Yacht Co.

1. At the dock in Taiwan
Stainless steel protector on rub rail
Notice the temporary documentation numbers on the flybridge

2. Transom and swim platform with teak decking
Aft deck video camera
Aft boarding doors installed
Explanatory Note: One of the great features of this boat is the protected main deck walkways, which will be great for the Furry Kid (Kodi) and granddaughter Amelia Myrna.

3. Aft deck
Settee awaiting cushions
Port side boarding door
Covered outlet on base of settee
Light switches on starboard side

4. Aft deck looking to port
Salon door with latch and lock installed
Outdoor "bar" with refrigerator, sink and storage cabinets
Fresh water wash down (perfect location)

5. Flybridge
Ladder to the hardtop
Inspection plates still uncov
Stainless steel rails on hardtop to assist with climbing up and down
Outlet next to grill

6. Flybridge looking forward

7. Flybridge control station (uncovered - hurrah)
Awaiting smoked glass windscreen
12 volt and 110 outlets on left of control panel
 
Explanatory Note: Equipment from left to right and top to bottom: 
- 2 Garmin GMI 10s flanking the Garmin 7215 multifunction screens
- Spotlight controller, compass, Caterpillar engine monitors, ABT TRAC stabilizer control
- Engine start/stop switches flanking VHF speaker
- Hydraulic bow and stern thruster controls
- Furuno autopilot
- Glendenning engine controls
- Garmin VHF microphones and control flanking helm

8. Flybridge looking to port
Settee and table awaiting cushions
Sliders on table

9. Flybridge looking to starboard
Refrigerator, sink and storage cabinets
Fresh water wash down (blue take on right cabinet wall)

10. Boat deck looking aft
Ladder to hardtop
Stainless steel grab rail for climbing up or down forward of hatch

11. VIP - No change

12. Guest head vanity, sink, medicine cabinet and stall shower
Tecna electronic head controls
 

13. Washer and dryer with ventilated door

14. Guest stateroom
Note the leeboard laying flush on the lower bunk
Door for forward head vanity awaiting installation

15. Master stateroom looking to port
Awaiting Shoji screens

16. Master head vanity, sink and medicine cabinet

17. Master SR looking aft
Entertainment center equipment awaiting installation (not in final location)

18. Stairwell leading to the accommodations
Banister
Access to wheelhouse control console with louvered door for proper ventilation

19. Pilot house looking forward (a bit messy)
Drawer sitting on the port side of the control station awaiting installation under settee
 

20. Stairwell to the flybridge
The covered newel posts are trimmed in wenge to fit in perfectly with the pilothouse design highlights
Explanatory Note: From left to right you can see the file drawer, fire control activator, the wine cooler, small pantry door, GE Monogram side by side refrigerator and (just barely) the large pantry door.

We were very concerned that the stairwell, as depicted in our CAD drawings (plans), would not be consistent with our decisions to have a modern look (i.e., smooth face cabinets, wenge trim, recessed ceiling with stainless steel handholds).  It was very conventional as shown in the photo below. 

20a. Conventional stairwell depicted in our plan drawings
Tania, on their own, installed the contemporary version.  We discovered the change in the photo below (Week 35 photos).

20b. Early Christmas present showing modern stairwell 
 This is what the finished product will look like:

20c. New
Again, this is really a big deal.  The conventional stairwell would have stuck out like a sore thumb.  This is just another example of Outer Reef exceeding our expectations.

21. Starboard side of the galley
There are storage drawers behind the doors on either side of the refrigerator

22. Galley to looking to port
Nice view of the sink, louvered cabinet door below the sink, microwave, cook top and stove
The large window makes the galley a cheerful place

23. Galley looking aft
Trash compactor awaiting teak veneer façade
Teak veneer façade waiting to be installed
Protective film on the glass

24. Salon looking forward
Nice view of the teak floor and wenge trim line (for the first time)

25. Salon looking aft
Protective film on the glass
 

26. Engine room looking forward
Awaiting installation of catwalk

27. Engine room looking aft

28. Lazarette looking forward
Awaiting catwalk coin dot flooring

29. Lazarette looking to port

30. Lazarette looking to starboard
Catwalk floor boards awaiting installation
Door on storage shelves over auxiliary tank

31. Lazarette looking aft with storage cabinets open
Shelves to starboard (left), hanging locker to port (right)
Temporary stairwell
Awaiting removable stainless steel ladder leading from the swim platform to the lazarette

32. Lazarette looking aft with storage cabinet door closed
Predictions: Next week or the week after  the photos will show the boat out of the water and, perhaps, we will see the final bottom paint and the boot stripe.  Continual testing of systems that require raw water is being done by equipment supplier's technicians.  Completion must occur before the boat is lifted.

Other news: We have agreed to exhibit the boat in two shows in the month of March, a PassageMaker Trawlerfest in Lake Park Florida (2/25 to 3/1) and the Palm Beach Boat Show (3/20 to 3/23).  This is in addition to the Miami Boat Show (2/14 to 2/18). 

This necessitated a significant change in plans.  Originally, we planned to cruise north to Sarasota immediately following the Miami show where we planned to spend the winter months (February through Early April).  Then starting in mid April we planned to cruise east via the Okeechobee Water Way and then up the coast to Massachusetts with a goal of arriving in mid to late May.

The current plan is to do a shake down cruise during the period from the end of the Miami show on  2/18 to the beginning of the Lake Park Show.  The plan is to cruise to Key West and then return east arriving in Lake Park on or about March 24.  My daughter, Lesley, soon to be son-in-law, Scott, and granddaughter Amelia (who will be 16 months) will accompany me.

Following the Trawlerfest we will cruise north to Stuart Florida where we will hang out at the Loggerhead Marina for a month (3/2 to 3/18 and 3/24 to 4/2).  We will cruise down to Palm Beach for the show.  The trek north will start in early April with a leisurely run up the intracoastal waterway to Norfolk and then a beeline from Norfolk to the Cape Cod Canal (approximately 500 miles or 5 day on the water).  Stay tuned for more details.

Written by Les.

Friday, November 15, 2013

Construction: Week 47 - Almost There

The title of this article, "Almost There," really says it all.  The list of items that are awaiting installation in Taiwan is very short.  I've noted these items for each photo along with some of the items that will be installed during commissioning in Florida.

Enjoy.

1. Guided Discovery still in the water
Bow plate (a bit hard to see)
Six man life raft installed on starboard rail
Windshield wipers
Spotlight on brow of flybridge (just above the windshield)
Flagpole mounted on bow rail
 Awaiting installation:
  • Taiwan: Bow seat cushions, Glendenning remote control system, bottom paint and boot stripe
  • Florida: Marquip Boarding Ladder, EZ2CY hardtop enclosure


2. Flybridge
Cover on grill
VHF antenna on either side of hardtop
Fiberglass boxes on the boat deck lights (2) mounted on the hardtop
Glendenning remote plug-in
 Awaiting installation:
  • Taiwan: Stidd helm chair base, plexiglas wind deflector, settee cushions
  • Florida: Stidd helm chair seat and post

3. Boat Deck
Six man life raft mounted to starboard rail
Flagpole
110 Volt outlet for dingy batter charger (just to left of the flagpole)
 
Awaiting installation:
  • Taiwan: None
  • Florida: Dingy (see below)
Explanatory Note: This week we made our final decisions on the dingy and its equipment.  It will be an AB Nautilus 13 DLX with 60 HP Yamaha equipped with a Garmin 541s multifunction display that will have a GPS, chart plotter and color display depth sounder (utilizing an in hull transducer). The Garmin 541s will me mounted on top of the console.  We chose this model as it has a 5" screen non glare screen.  The boat will also have two Yamaha digital gauges; one displaying speed and fuel and the other RPM and trim.  A special mount will enable us to clip in our ICOM M36 VHF.  We also order a custom cover (Aqualon white) and a swim ladder.

The 13 DLX is a 13 foot rib (like our 11 foot Caribe).  With 60 HP it should have a top speed of 35 MPH and cruise comfortably at 30 MPH with two aboard.  The 13 DLX has seating for 5.  We expect that it will be able to get on plane with 4 persons, which our 30 HP Caribe could not do.

The 13 DLX weighs in fully equipped at 1,000 pounds.

3a. 13 DLX Overview

3b. AB Nautilus 13 DLX


4. VIP Stateroom - Finished
 
 Awaiting installation:
  • Taiwan: None
  • Florida: Mattress, decorative spread, shams and pillows
5. Guest Stateroom - Finished
Door mounted on hanging lockers
Worker installing lee board on lower bunk (for Amelia Myrna)
 Awaiting installation:
  • Taiwan: None
  • Florida:  Mattress, decorative spread, shams and pillows
6. Master Stateroom
Wall paper around port holes
 
  Awaiting installation:
  • Taiwan: Shoji screens
  • Florida:  Mattress, decorative spread, shams, pillows and carpeting
6a. Our shoji screens sitting in the carpentry shop

7. Master Stateroom looking aft
Door and drawers on the locker next to the engine room
Door on port hanging locker
Door on starboard hanging locker
Inside door to engine room
Watertight door protected
Ceiling complete
 Awaiting installation:
  • Taiwan: None
  • Florida:  Mattress, decorative spread, shams, pillows and carpeting
7. Pilothouse
Windshield wipers
Glendenning single lever controls (right of helm)
Outlets at the base of the settee
Ceiling rails protected
 Awaiting installation:
  • Taiwan: Stidd helm chair base, settee cushions
  • Florida:  Stidd helm chair seat and post 
8. Pilothouse looking to starboard
VHF installed
Stairwell finished with protected wenge newel posts
Wine cooler under stairwell
File drawer installed
Stairs with black Bolon treads (protected)
Fireboy emergency activator
 Awaiting installation:
  • Taiwan: None
  • Florida:  None
9. Galley looking to port and aft
Ceiling & lighting
Stainless steel ceiling rails
Cabinet door under sink
Drawers next to dishwasher
Trash compactor (left of dishwasher) still missing teak cover
 Awaiting installation:
  • Taiwan: Teak facade on trash compactor
  • Florida:  None
10. Salon looking forward
Ceiling & lighting
Stainless steel hand holds
Rope lighting illuminated
 Awaiting installation:
  • Taiwan: Settee cushions
  • Florida:  Barrel chairs (2), decorative pillows, area rug and window treatments
11. Salon looking aft
Recessed ceiling and lighting
Stainless steel hand holds on ceiling
Rope lighting illuminated

12. Engine room looking forward - No change
 Awaiting installation:
  • Taiwan: Catwalk coin-dot flooring
  • Florida: Tool chest mounted in the tray over the port engine
13. Engine Room looking aft - No change

14. Lazarette looking to port
____________ on forward bulkhead
 Awaiting installation:
  • Taiwan: Catwalk coin-dot flooring
  • Florida:  Hooks to hold our bikes
15. Lazarette looking to starboard - No change
 Awaiting installation:
  • Taiwan: Catwalk coin-dot flooring, stairwell from the swim platform to the lazarette
  • Florida:  None
As usual, my prediction that the sea trial would take place last week appears to be incorrect.  Perhaps this week?

According to Outer Reef, she will be finished in two weeks and then, hopefully, on her way to Fort Lauderdale.

Expected Shipping Date: December 15, 2014.  Expected Arrival Date: January 15, 2014.

Written by Les